Purpose
The First Article Inspection skill provides capabilities for planning and executing first article inspections per AS9102, enabling comprehensive verification of manufacturing processes and design conformance.
Capabilities
- FAI plan development per AS9102
- Balloon drawing preparation
- Measurement method specification
- CMM programming guidance
- Characteristic accountability matrix
- Partial FAI and delta FAI management
- FAI report generation (Forms 1, 2, 3)
- Non-conformance disposition
Usage Guidelines
AS9102 Requirements
FAI Triggers
Full FAI required when:
- New part number
- Design change affecting form/fit/function
- Change in manufacturing process/location
- Tooling inactive > 2 years
- Manufacturing process change
- Natural/human-made event affecting process
Partial FAI (Delta FAI)
Allowed when:
- Minor design change
- Controlled process change
- Tooling modification
Only affected characteristics need re-inspection
FAI Planning
Characteristic Identification
-
Drawing Review
- Identify all dimensions
- Identify all notes
- Identify material/process requirements
- Identify special characteristics
-
Characteristic Types | Type | Symbol | Definition | |------|--------|------------| | Standard | None | Normal inspection | | Critical | Triangle/diamond | Safety/function critical | | Major | M in circle | Important for assembly | | CTQ | Key symbol | Customer specified |
Balloon Drawing
Ballooning requirements:
- Unique number for each characteristic
- Sequential numbering preferred
- Reference to original dimension
- Include notes and specifications
- Mark special characteristics
AS9102 Forms
Form 1: Part Number Accountability
Required fields:
- Part number and name
- Part revision level
- Drawing number and revision
- Organization name and code
- FAI report number
- Signature and date
- Part serial number
- FAI reason (new/change)
Form 2: Product Accountability - Materials, Processes, Functional Testing
Material verification:
- Material specification
- Raw material supplier
- Material certifications
- Heat/lot traceability
Process verification:
- Special processes (heat treat, plating, NDT)
- Process specification
- Processor certification
- Process parameters
Functional testing:
- Test requirements
- Test results
- Pass/fail status
Form 3: Characteristic Accountability
For each characteristic:
- Characteristic number (balloon)
- Reference location (drawing zone)
- Characteristic designator (if special)
- Requirement (nominal and tolerance)
- Results (actual value)
- Designed tooling (Y/N)
- Non-conformance number (if applicable)
Measurement Methods
Measurement Selection
| Tolerance | Accuracy Required | Typical Method | |-----------|------------------|----------------| | +/- 0.5 mm | 0.05 mm | Caliper | | +/- 0.1 mm | 0.01 mm | Micrometer | | +/- 0.025 mm | 0.002 mm | CMM | | +/- 0.005 mm | 0.0005 mm | Precision CMM |
GD&T Measurement
| Characteristic | Measurement Method | |----------------|-------------------| | Flatness | CMM scan, optical flat | | Perpendicularity | CMM, square fixture | | Position | CMM, functional gage | | Concentricity | CMM, roundness tester | | Runout | V-blocks + indicator | | Profile | CMM, optical comparator |
CMM Programming
CMM measurement strategy:
1. Establish datum reference frame
2. Measure datum features first
3. Measure located features
4. Use appropriate probe compensation
5. Verify measurement uncertainty
6. Document probe configuration
Non-Conformance Handling
Disposition Options
| Disposition | Application | Authority | |-------------|-------------|-----------| | Use As-Is | Minor deviation, no impact | Engineering | | Rework | Can be brought to spec | Quality | | Repair | Alternate method to restore | Engineering | | Scrap | Cannot be made conforming | Quality | | Return to Supplier | Vendor issue | Purchasing |
Documentation Requirements
Non-conformance record:
- NC number
- Characteristic affected
- Requirement
- Actual condition
- Root cause analysis
- Corrective action
- Disposition and approval
FAI Approval Process
Approval workflow:
1. Inspector completes inspection
2. Quality review forms
3. Engineering review (if NC exists)
4. Quality approval signature
5. Customer approval (if required)
6. Archive and distribution
Process Integration
- ME-023: First Article Inspection (FAI)
Input Schema
{
"part_info": {
"part_number": "string",
"revision": "string",
"description": "string",
"drawing_number": "string"
},
"fai_type": "full|partial|delta",
"trigger": "new_part|design_change|process_change|other",
"previous_fai": "string (if partial/delta)",
"special_requirements": {
"customer_approval": "boolean",
"special_processes": "array"
}
}
Output Schema
{
"fai_plan": {
"fai_number": "string",
"balloon_drawing": "file reference",
"characteristic_count": "number",
"measurement_methods": "array"
},
"fai_forms": {
"form_1": "document reference",
"form_2": "document reference",
"form_3": "document reference"
},
"results_summary": {
"total_characteristics": "number",
"conforming": "number",
"non_conforming": "number",
"nc_numbers": "array"
},
"approval_status": {
"status": "approved|conditional|rejected",
"conditions": "array (if conditional)",
"approved_by": "string",
"date": "date"
}
}
Best Practices
- Review drawing completely before ballooning
- Ensure measurement method capability
- Document traceability to raw material
- Obtain certifications for special processes
- Address all non-conformances before approval
- Maintain FAI records per retention requirements
Integration Points
- Connects with GD&T Drawing for requirements
- Feeds into Design Review for verification evidence
- Supports Process Planning for capability verification
- Integrates with Quality systems for record keeping