Agent Skills: Project Estimation

Estimate project scope, timeline, and resource requirements using multiple estimation techniques including bottom-up, top-down, and analogous estimation methods for accurate project planning.

UncategorizedID: aj-geddes/useful-ai-prompts/project-estimation

Install this agent skill to your local

pnpm dlx add-skill https://github.com/aj-geddes/useful-ai-prompts/tree/HEAD/skills/project-estimation

Skill Files

Browse the full folder contents for project-estimation.

Download Skill

Loading file tree…

skills/project-estimation/SKILL.md

Skill Metadata

Name
project-estimation
Description
>

Project Estimation

Table of Contents

Overview

Accurate project estimation determines realistic timelines, budgets, and resource allocation. Effective estimation combines historical data, expert judgment, and structured techniques to minimize surprises.

When to Use

  • Defining project scope and deliverables
  • Creating project budgets and timelines
  • Allocating team resources
  • Managing stakeholder expectations
  • Assessing project feasibility
  • Planning for contingencies
  • Updating estimates during project execution

Quick Start

Minimal working example:

# Three-point estimation technique for uncertainty

class ThreePointEstimation:
    @staticmethod
    def calculate_pert_estimate(optimistic, most_likely, pessimistic):
        """
        PERT formula: (O + 4M + P) / 6
        Weighted toward most likely estimate
        """
        pert = (optimistic + 4 * most_likely + pessimistic) / 6
        return round(pert, 2)

    @staticmethod
    def calculate_standard_deviation(optimistic, pessimistic):
        """Standard deviation for risk analysis"""
        sigma = (pessimistic - optimistic) / 6
        return round(sigma, 2)

    @staticmethod
    def calculate_confidence_interval(pert_estimate, std_dev, confidence=0.95):
        """
        Calculate confidence interval for estimate
        95% confidence ≈ ±2 sigma
        """
        z_score = 1.96 if confidence == 0.95 else 2.576
// ... (see reference guides for full implementation)

Reference Guides

Detailed implementations in the references/ directory:

| Guide | Contents | |---|---| | Three-Point Estimation (PERT) | Three-Point Estimation (PERT) | | Bottom-Up Estimation | Bottom-Up Estimation | | Analogous Estimation | Analogous Estimation | | Resource Estimation | Resource Estimation | | Estimation Templates | Estimation Templates |

Best Practices

✅ DO

  • Use multiple estimation techniques and compare results
  • Include contingency buffers (15-25% for new projects)
  • Base estimates on historical data from similar projects
  • Break down large efforts into smaller components
  • Get input from team members doing the actual work
  • Document assumptions and exclusions clearly
  • Review and adjust estimates regularly
  • Track actual vs. estimated metrics for improvement
  • Include non-development tasks (planning, testing, deployment)
  • Account for learning curve on unfamiliar technologies

❌ DON'T

  • Estimate without clear scope definition
  • Use unrealistic best-case scenarios
  • Ignore historical project data
  • Estimate under pressure to hit arbitrary targets
  • Forget to include non-coding activities
  • Use estimates as performance metrics for individuals
  • Change estimates mid-project without clear reason
  • Estimate without team input
  • Ignore risks and contingencies
  • Use one technique exclusively