Agent Skills: Florida Environmental Permitting Skill

Florida environmental permitting expertise. Invoke for SJRWMD permits, wetland assessments, flood zone analysis, or stormwater requirements.

UncategorizedID: breverdbidder/spd-site-plan-dev/environmental-permitting

Install this agent skill to your local

pnpm dlx add-skill https://github.com/breverdbidder/spd-site-plan-dev/tree/HEAD/.claude/skills/environmental-permitting

Skill Files

Browse the full folder contents for environmental-permitting.

Download Skill

Loading file tree…

.claude/skills/environmental-permitting/SKILL.md

Skill Metadata

Name
environmental-permitting
Description
"Florida environmental permitting expertise. Invoke for SJRWMD permits, wetland assessments, flood zone analysis, or stormwater requirements."

Florida Environmental Permitting Skill

When to Invoke

  • Questions about SJRWMD permits
  • Wetland assessment needs
  • Flood zone determination
  • Stormwater management
  • Environmental constraints

SJRWMD Permit Types

ERP (Environmental Resource Permit)

Required for:

  • Projects disturbing >1 acre
  • Work in wetlands
  • Stormwater systems
  • Activities in/near surface waters

Thresholds:

  • <4,000 sq ft impervious: Exempt
  • 4,000 sq ft - 1 acre: Noticed General
  • 1 acre: Individual permit

WUP (Water Use Permit)

Required for:

  • Irrigation systems >1 acre
  • Commercial water use
  • Dewatering operations

Flood Zone Determination

FEMA Zone Designations

| Zone | Risk Level | Requirements | |------|------------|--------------| | X | Minimal | Standard construction | | A | High (no BFE) | Elevation required | | AE | High (BFE known) | Build above BFE | | VE | Coastal high hazard | Strict requirements |

Building Requirements by Zone

  • Zone X: No special requirements
  • Zone A/AE: Lowest floor ≥ BFE + 1 ft
  • Zone VE: Open foundation, ≥ BFE + 1 ft

Wetland Assessment Process

  1. Desktop Review

    • Check National Wetlands Inventory (NWI)
    • Review aerial imagery
    • Identify potential wetland areas
  2. Field Delineation (if needed)

    • Hire certified wetland delineator
    • Flag wetland boundaries
    • Prepare delineation report
  3. Permit Strategy

    • Avoid: Best option
    • Minimize: Reduce impact
    • Mitigate: Compensate for unavoidable impact

Stormwater Requirements

Retention/Detention

  • Pre vs post development runoff
  • 25-year, 24-hour storm
  • Water quality treatment

Common Solutions

  • Retention ponds
  • Dry detention
  • Swales
  • Underground systems

Timeline Estimates

| Permit | Review Time | |--------|-------------| | ERP General | 30 days | | ERP Individual | 90 days | | WUP | 90 days | | Wetland Delineation | 30-60 days |

Key Contacts

  • SJRWMD: 386-329-4500
  • FDEP: 850-245-2118
  • US Army Corps: 904-232-1666